Gold Mine Bridge


SS&PF was awarded this design/build bridge project mid-September with a critical pick date of November 11th.  SS&PF worked around the clock to complete the design, fabrication, and apply a three-part paint system for the entire 140′ span.  The (3) sections were delivered on time and under budget.  Rapid response and tough deadlines are our forte!      